When beginning to minimize waste during a construction project, what is the first action that should be taken?

Practise this LEED GA Green Building Prep question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
Multiple choice — select the best answer
✓ Correct answer: C. Implement source reduction Answer: Implement source reduction Implementing source reduction is the first step in minimizing construction waste by preventing materials from becoming waste in the first place. Setting recycling goals, developing a waste audit, and establishing a waste tracking system are important but follow after initial waste reduction efforts have been addressed.

Keep practising. Use the free LEED GA Green Building Prep PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.

Keep practising

Related questions

Free practice here. Timed mocks when you are ready.

Study the LEED GA Green Building Prep free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.