Which of the following is NOT a risk factor when implementing an agile project management approach?

Practise this CRISC IT Risk Exam Prep question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
Multiple choice — select the best answer
✓ Correct answer: C. Project finishes ahead of schedule Answer: Project finishes ahead of schedule An agile project management approach often involves iterative cycles, frequent testing, and constant feedback. These characteristics can lead to challenges such as managing frequent changes, ensuring proper collaboration among team members, and maintaining the project scope. Finishing ahead of schedule is not typically considered a risk factor.

Keep practising. Use the free CRISC IT Risk Exam Prep PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.

Keep practising

Related questions

Free practice here. Timed mocks when you are ready.

Study the CRISC IT Risk Exam Prep free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.