In the context of project management, how does the Gantt chart differ from the Work Breakdown Structure (WBS)?
Practise this CISA Audit Exam Prep 2026 question free, then download the PDF, watch the video walkthrough, or unlock timed mock exams for the full web bank.
AGantt charts outline resource dependencies, while WBS organizes team roles.
BA Gantt chart visually represents the project schedule, while WBS breaks down the project's deliverables.
CA Gantt chart is used for resource allocation, while WBS focuses on project cost estimation.
DGantt charts are used for risk management, while WBS manages project scope.
✓ Correct answer: B. A Gantt chart visually represents the project schedule, while WBS breaks down the project's deliverables.A Gantt chart is a graphical tool that represents the project schedule, showing activities against time. It helps project managers track progress and manage time effectively. A Work Breakdown Structure (WBS), on the other hand, decomposes the project's deliverables into smaller, manageable components, making it easier to assign responsibilities and track deliverables.
Keep practising. Use the free CISA Audit Exam Prep 2026 PDF, watch the YouTube walkthrough, or unlock all 10 web questions with timed mock exams.
Free practice here. Timed mocks when you are ready.
Study the CISA Audit Exam Prep 2026 free question explanations, download the PDF, then unlock timed mock exams on the web when you want exam-day practice.